 |
UNITED NATIONS DEVELOPMENT PROGRAMME IN
PAKISTAN
SUSTAINABLE DEVELOPMENT NETWORKING PROGRAMME
PROJECT NUMBER: : PAK/95/006
PROJECTBUDGET REVISION DOCUMENT
UNITED NATIONS DEVELOPMENT PROGRAMME BUDGET REVISION
Country: Pakistan
Number: PAK/95/006
Title: Sustainable Development Networking Programme
Last Revision date: 22December3 December 1996
The attached budget of the above project is hereby revised to cover
the extension period of the project up to April 1999 including an increase
in the UNDP input of US$ 200,000 as per justification given in this document.
The change to the project budget, the UNDP input is as follows:
Previous UNDP Input - Project budget code "B" $ 61,500
Revised UNDP Input - Project budget code "C" $ 261,500
UNDP Input Increase $ 200,000
AOS Input $ 46,214
TABLE OF CONTENTS
A. CONTEXT AND BACKGROUND 21
B. PROJECT JUSTIFICATION 21
C. DEVELOPMENT OBJECTIVE
D. IMMEDIATE OBJECTIVES
E. INPUTS
F. RISKS
G. PRIOR OBLIGATIONS AND PREREQUISITES
H. PROJECT REVIEW, REPORTING AND EVALUATION
I. LEGAL CONTEXT
JI. UNDP BUDGETS
K.J. ANNEXES
ANNEX I. Work plan
ANNEX II. Job descriptions
ANNEX III. Schedule of project reviews, reporting and evaluation
ANNEX IVII. Financial and accounting arrangements
ANNEX IV. Budget estimate and assumptions
ANNEX V. Request for waiver
ANNEX VI. Sub-contract
A. CONTEXT AND BACKGROUND
The Sustainable Development Networking Programme in Pakistan was started
by UNDP in 1992 by UNDP and managed by IUCN. It and it has been working
since then to promote access to information on sustainable human developmentsustainable
development by different sectors of society. When it started, there was
little electronic networking in Pakistan and SDNP was a pioneer in promoting
the use of electronic mail and computer networks in general in Pakistan.
Since there was no generally available networking infrastructure at
the start of the project, SDNP had to invest considerable effort in establishing
such a network. These efforts, along with a dramatic rise of interest in
the Internet globally, have led to significant developments around the
Internet in Pakistan. There are now a number of private-sector Internet
Service Providers (ISPs) who provide connectivity for a fee. Thus SDNP
can now focus its efforts on promoting the availability and exchange of
quality information on sustainable human developmentsustainable development;
this is what is planned for the extension phase, described in this document.
B. PROJECT JUSTIFICATION
1. Problem to be addressed
A brief overview of the project and progress thus far has been provided
to put the revision in perspective.
SDNP has been operational since December 1992. It has been supported
from the start by IUCN Pakistan, who have been much more than traditional
managers of a project – providing advice and direction on almost a day-to-day
basis. During this period, SDNP During this period, it has successfully
achieved the objectives proposed, by setting up operational email nodes
in four major cities (Islamabad, Karachi, Lahore and Peshawar) with a large
number of users (around 4,500 nodes). SDNP has also played a major role
in raising awareness about the use of electronic networks and trained a
large number of users in this. In addition, it has undertaken other activities
to promote electronic information in Pakistan, such as creating repositories
for public domain software, setting up electronic bulletin boards, working
with other networking groups, and providing good technical support to users.
SDNP has been active in Internet education in Pakistan, conducting free
weekly workshops and having on-line response to queries. SDNP also hosts
Cybermart, a daily electronic leaflet for advertisements and announcements.
SDNP's email service has operated successfully on a cost-recovery basis,
an innovation suggested by IUCN that has positively affected the project
and the design of the new phase.
SDNP's email service has operated successfully on a cost-recovery basis.
Apart from connectivity, SDNP's mandate was to further information exchange
related to sustainable human development. To achieve this, SDNP has setup
various electronic mailing lists and discussion groups on thematic areas
like environment, health, economics, women's issues and so on. SDNP subscribes
to international newsgroups for some of these and distributes them to its
members. Also Pakistan-wide discussion groups have been setup and are exchanged
with other networks in Pakistan. Numerous periodicals related to SHD are
distributed on the network. SDNP also works with the Sustainable Development
Policy Institute to setup a clipping service (maintained by SDPI and hosted
by SDNP) on environment, economic planning and development, agriculture
and national security.
SDNP has provided consultancy free of charge to organizations working
in the development sector to help them with their communication needs.
SDNP has also helped organizations get vital information, some of which
was used to deal with emergencies. Some of this information has helped
in disaster management, public litigation and policy planning. One such
incident was the help provided to Shirkat Gah-Women’s Resource Center,
Lahore to get critical information related to a chlorine gas poisoning
accident. However, such activities have been conducted mostly on an informal
and ad hoc basis, answering queries when received.
SDNP has also assisted in setting up a local web server with web pages
for SDNP, UNDP and Edunet, bringing the entire resources of Edunet -- the
largest educational database (600MB) in Pakistan with thousands of articles
on various topics -- on-line. At the moment, it is only a trial service
accessible in Islamabad and Lahore.
Thus SDNP has been instrumental in initiating a number of activities
to help achieve the development objectives of the project and to promote
sustainable human developmentsustainable development. It has made some
efforts to improve the implementation of Agenda 21 through the NCS in Pakistan
by facilitating increased access to information, knowledge and expert advice
and by increased communications between stakeholders locally, nationally
and globally. This has been all the more possible because of its association
with IUCN Pakistan, as IUCN’s own member and partner networks have been
shared with SDNP. In addition all the SDNP offices have been housed within
IUCN’s programme offices It has helped that, with the exception of the
node in Lahore. This has helped to engender greater understanding of sustainable
development among SDNP staff, all the SDNP offices are housed within IUCN’s
programme offices.
Based on discussions with various target beneficiaries the following
picture emerges:
- A lack of organized information on sustainable human development
-
Time and resources wasted looking for information because of lack of training.
-
High cost of organizing and disseminating information, and duplication
of efforts by different agencies.
SDNP has done an excellent job during the initial phase of setting
up an electronic network. Now that the infrastructure is present, it is
time to move on to the task of helping organizations develop and implement
an "information strategy", training staff in how to look for information
on the Net, what information is worth publishing electronically, helping
them setup of web pages, and so on.
To achieve these objectives, SDNP’s existing network infrastructure
needs to be put to good use. It will need to be upgraded to full Internet
(with at least a 64kbps link to the Internet) to access information effectively,
but the project’s major efforts will be to help create repositories of
sustainable human developmentsustainable development information on-line,
and to build capacity in institutions to manage and use this information
effectively.
The existing infrastructure (after being upgraded to full Internet)
can be used for achieving the following objectives, which are:
- Improving the capacity of the beneficiaries to effectively
utilize existing information.
- Improving the capacity of the beneficiaries to access sustainable
human developmentsustainable development information.
- Improving the capacity of the beneficiaries to organize and
disseminate development information.
- Ensuring that SDNP is a sustainable entity at the end of the project
period.
It was agreed by all parties in the first tri-partite meeting
that the project should now place more emphasis on building capacity within
Pakistan's public and not-for-profit sectors to utilize the current information
and communication technologies effectively for the promotion of sustainable
human developmentsustainable development and to interact with and benefit
especially from the resources available on the Internet. The main function
of the emerging SDNP will be facilitation of access to information on sustainable
human developmentsustainable development to the target groups. Since the
current contractual arrangement under which the project operates ends,
in April 1997, (?) the project needs to be extended by 2
years untill March 2000April 1999 to complete theits development objectives.
2. Expected end of project situation
With efforts focused more on the development objectives and on the target
beneficiaries, the situation at the end of the project period is expected
to improve considerably particularly in the following areas:
Improved access to existing information
- SDNP will be a repository of meta-information, providing pointers
to information or databases available elsewhere. AAt the end of this effort,
it is expected that the utilization of the existing information will improve.
- While SDNP will not develop any databases, it will assist organizations
to improve dissemination of information or databases, especially using
electronic networks.
Improved capacity to access information
The capacity of target beneficiaries to access sustainable human developmentsustainable
development information will have been considerably improved. The target
organizations would be connected to the Internet, with staff trained in
using electronic networks to find information and to interact with each
other.
Improved capacity to organize, and disseminate information
and impart training
SDNP would also help other organizations devise an "electronic information
policy", on what existing information of theirs should be made available
electronically or on-line, and how organizations could network with one
another to utilize information more effectively.
Some of these organizations may setup web servers of their own; others
may just create web pages hosted at a suitable ISP.
The strategy that will be employed, is to work with organizations
to strengthen their information capabilities, and depend on them for outreach
to other organizations.
Capacity of target beneficiaries to impart training
The project will develop capacity within selected institutions to act
as resource centers and train others in the use of information technology.
SDNP ais a sustainable entity
A detailed midterm review/feasibility study will be undertaken after
a year to come up with the best option for sustaining the current work
of SDNP after the 2-year period. The study will focus on how SDNP can become
a self sustaining not-for-profit entity promoting its current development
objectives after the 2-year period.
3. Target beneficiaries
The primary focus of the project is on those organizations that are
working with information in the area of sustainable human developmentsustainable
development. In this transition phase of the project, organizations which
are more receptive to adopting new technologies and are making some efforts
to develop information would be given preference. Support and subsidy will
be provided to only those institutions which are not in a position to invest
in such efforts. Those which have the rresources likesuch as Lahore University
of Management Sciences and Institute for Educational Development will not
be eligible for any subsidized services.
Target beneficiaries will belong to different sectors, and will
be selected according to their existing efforts in the field of information
for sustainable human developmentsustainable development, as well as the
potential benefit to all SDNP members of their information being available
on-line. Some possible beneficiaries are listed below.
Government
Ministry of Environment, Environmental Protection Agencies and Ministry
of Planning and Development, in Islamabad and the provinces will benefit
from training and connectivity. It is also proposed that SDNP provide input
into policy-making for information, networking and telecommunication in
Pakistan.
Academia and research institutions
These will benefit primarily from the training programmes. Just as SDNP
played a crucial role in popularizing the idea of electronic mail and networking,
it should now bring public attention, especially in academia, to the importance
of a coherent information strategy for all organizations.
NGOs
NGOs will benefit from all the project activities. Some may setup web
servers to publish information, others may attend training courses and
maybe act as trainers for their target audiences.
Development projects
Other projects working in the area of sustainable human developmentsustainable
development will benefit from assistance in their information needs.
Donors
Donor agencies will benefit from having more information about organizations
working for sustainable human developmentsustainable development, and more
information about past and ongoing projects. SDNP can also assist the donor
organizations themselves in working out an information strategy (for a
fee).
Business
Information policy is an important part of business today. When SDNP
develops a model for organizations to deal with information, this can be
marketed to the business community as something useful to them. This service
can eventually turn into a revenue stream for the project.
The specific organizations in each of these categories will be selected
keeping in mind the selection criteria.
4. Project sstrategy and implementation aarrangements
Project strategy
The strategy being adopted for the extension period is based on feedback
obtained in the first tri-partite meeting and lessons learnt during the
first phase. It aims at maintaining the focus on the development agenda
and working to ensure that the target audience is the major beneficiary
of SDNP. SDNPs globally work in three areas: connectivity, content (information)
and capacity-building (training). In Pakistan, so far much of the emphasis
has been placed on the connectivity angle (and understandably so, since
there was little or no connectivity infrastructure available when it, SDNP,
began in 19932), but it is now time to attend to the other two. All SDNP
activities are being planned so as to be sustainable in the long run. ?
Connectivity and future services
At present SDNP is providing email services to approximately 4,500 nodes
through its offices in Islamabad, Karachi, Lahore and Peshawar. These nodes
generate revenue of roughly Rs. 1,000375,000 /= per month. Technology has
moved on, and an email-only service is no longer acceptable as full Internet
is available in Pakistan, provided by a number of Internet Service Providers
(ISPs), and will be demanded by users. SDNP should not compete with the
commercial ISPs, rather it should concentrate on its niche in the area
of sustainable human developmentsustainable development. SDNP provides
connectivity at the moment, but it is a means to an end. The main value
added by SDNP is consultation on theirinstances,’ specific information
needs, a source of SHD information and training for users in the use of
e-mail and the Internet.
Since SDNP has been a leader in raising awareness about electronic
networking, it is in a good position to provide assistance in policy-making
in the field of telecommunications, information and networking. SDNP mailing
lists can be used to debate existing legislation, and recommendations put
forward to government and other parties.
SDNP's impartial position can also be useful in acting as a mediator
between the different Internet Service Providers to create a Pakistan Internet
Exchange (PIX) so that the different networks can exchange information
with each other within the country without going abroad and wasting precious
international bandwidth.
The overall strategy, therefore, is to benefit from the work already
done in the connectivity area (a large userbase which can broaden the scope
of SDNP as well as prove a source of revenue) and concentrate further efforts
in the region of information and training. In addition, a n SDNP provincial
node will be established in Quetta in December April 1999.? SDNP will work
to develop provincial information centers, housed at suitable institutions
which are interested in and capable of this sort of activity.
Information services and the future
In the new phase, SDNP is to focus on information for sustainable human
development, both in the provision of such information and its development.
This is to be done in a number of ways, as follows.
Improve access to existing information
SDNP will attempt to be a repository of "meta-information", a source
that can provide pointers to quality information available electronically
or otherwise, on specific topics related to Ssustainable Human Ddevelopment.
Typically sectoral information requirements that are of general interest
worlduld include the following:
- List of projects in a given subject and brief description.
- List of institutions and brief description.
- List of experts with brief resume.
- List of publications with abstract or summary.
- Quantitative information specific to the sector.
- NGOs with brief description of each.
- Information on seminars and itrelateds publications and important
recommendations.
- Information on training opportunities with details of the courses
and institutions.
- Technology advances and information of suppliers and vendors.
- List of journals and newsletters and possibly their contents.
- Government rules and regulations and laws.
- Government policies and major initiatives.
- Initiatives of the international donors.
- International information relating to the sector.
IUCN Pakistan’s environmental libraries in Karachi, Islamabad, Peshawar
and Quetta can assist in this task. Relevant information can be put on-line
or can point to existing web sites. For example, IUCN HQ is in the process
of creating a global Biodiversity Conservation Information System that
SDNP could tap into. In addition, both IUCN and WWF fund the World Conservation
Monitoring Centre that houses material on Pakistan’s biodiversity.
Capacity to access information
Access to information is dependent on being connected to e-mail and
the Internet and having the capacity to use these tools for getting the
relevant information. Thus SDNP will assist the target beneficiaries in
getting connected to the Internet and then train them ion using the necessary
tools. Some institutions may require financial assistance while others
may require only technical advice and training.
Capacity to organize and disseminate information
SDNP will focus on establishing centers of reliable information on Sustainable
Human Development and will follow two ways of achieving this.
One, SDNP will work with a suitable partner organization in each
province to establish a center of information either on the entire spectrum
of Ssustainable Human Ddevelopment or on a particular sector. Ideally,
these centers will not be located at SDNP offices, but within the partner
organization whose staff can be trained and who can eventually carry on
and promote this activity. SDNP will provide these organizations with personnel
to help to help them develop an information strategy and get started.
The aim is to build capacity in a variety of Pakistani institutions
so that they can publish information related to their activities electronically.
The SDNP web site can carry pointers to these information resources, and
perhaps mirror them for efficiency, but all maintenance and updating of
this information is to be carried onut by the "owners" of this information.
Two, SDNP will assist a number of organizations in designing an electronic
"information strategy" for themselves. For example, SDNP can help them
setup web pages, discuss the issue of regular updates (an issue often ignored
in this sort of strategy) and help them find a host for their web pages
if necessary.
Provide training
SDNP will be involved in a number of training initiatives.
One effort will focus on strengthening the capacity of other organizations
to act as trainers in the future, both in accessing electronic networks
for information (including how to search for information efficiently on
the Internet) and in providing information electronically.
The second effort will be to provide training on the above topics directly
to the beneficiaries. Some of this will be conducted through group workshops
and some at the organizations themselves.
SDNP as a sustainable entity
SDNP will continously examine the the options for sustaining the current
work after the 2-year period. It will focus on how SDNP can become a self
sustaining not-for-profit entity promoting its current development objectives
after the 2-year period
Implementation arrangements
SDNP will continue to be executed by the United Nations Office of
Project Services (UNOPS). UNOPS will sub-contract the implementation to
IUCN, as it has done before. The Ministry of Environment, Local Government
and Rural Development will be the Government Cooperating Implementing Cooperating
Implementing Agency. This arrangement has worked satisfactorily in the
past and all partners are in agreement into continuinge it. A feasibility
study which will include a business plan will be carried out during the
transition period to work out the modalities of SDNP becoming a permanent
sustainable entity on its own after the project.
The project activities are such that divided into two halves, a Connectivity
Services component and an Information Services component. UNDP/Pakistan
funding (through PAK/95/006) will be used for certain budget lines the
information component, while the connectivity component will be financed
from savings and interest from e-mail activities of the previous phase
as well as projected revenues generated revenues during the extension phase
will fund others. A separate accounting entity will be established to account
for the income and expenditure of the connectivity component.
5. Reasons for UNDP assistance
The Assistance from UNDP is required for the project as the lead responsibility
for further promoting this SDNP concept has been given to remains with
UNDP. Along with IDRC, it has been providing the resources for the project
to date. IDRC is not in a position to fund the project anymore. Thus being
the initiator, it is logical that UNDP fund the transition period as well
so that the project is successful in achieving its long term objectives.
The assistance will ensure that the project is successfully converted into
a sustainable entity. The Government of Pakistan is not in a position to
provide funding for this project. Other donors are also reluctant to provide
funds as they believe that UNDP is responsible for this project.
6. Special considerations
At this stage of the project there are a number of issues which need
special attention. These are presented below:
The project needs to ensure that special attention is paid to link the
activities to Sustainable Human D development and to the implementation
of the NCS.
In the past, due to the poor electronic networking environment, the
basic infrastructure had to be developed. In the future, the development
agenda must be given priority over the connectivity.
7. Coordination arrangements
Role of UNOPS
The United Nations Office for Project Services (UNOPS) will be the
Executing Agency. It will implement execute the project through a sub-contract
with IUCN. However, UNOPS will directly implement an independent end-of-project
evaluation if requested.
Role of IUCN
IUCN under a sub-contract with on behalf of UNOPS will continue to implement
the project in Pakistan. It will be responsible for the overall management
of the project. IUCN will ensure that the project is implemented according
to the approved Project Revision Document and as per the agreed schedule.
IUCN will provide regular progress as well as financial reports to UNDP.
As in the past, IUCN will be much more than project managers – they will
assist the SDNP team take innovative actions in the field of environmental
communications.
IUCN Management Team
Since overall project coordination will be carried out by IUCN, the
organizationlatter will form a management team of two persons specifically
for this purpose. One person will assist in offering advice on policy,
personnel and day-to-day financial management, while the other will advise
on the programmatic aspects of the project, for example on the choice of
provincial institutions and more importantly, on sustainable human development..
IUCN’s experience in publishing information will also be used towards web
publishing.
These will not be IUCN staff dedicated solely to SDNP but will be giving
a percentage of their time to the above activities.
This arrangement will ensure IUCN's timely input as well as delivery
of outputs.
Role of UNDP Pakistan
UNDP Pakistan's main role would be to provide guidance and financial
support to the project. whenever required. Its help will be needed when
dealing with the Government of Pakistan especially on issues which relate
to the proper functioning of SDNP. It may also be called upon to request
for licenses and permits which may be needed for operating electronic networks.
UNDP will also be effective in helping SDNP link up with other UNDP projects,
which are likely to find SDNP services useful. Finally, UNDP Pakistan will
participate in the inteviews of the candidates for the Programme Director
post and approve the final selection.
Role of SDNP, New York
SDNP New York will continue to provide advice and technical support
but without any financial obligations to the project. Their input will
be useful in bringing experiences from a number of other SDNPs around the
world, but SDNP in Pakistan will be free to evolve its own policies and
guidelines keeping in view the national environment.
Role of the Ministry of Environment, Local Government and Rural Development
The Ministry is the Government Cooperating Cooperating/Implementing
Agency of the project and will continue to remain so during the extension
phase as well. The Ministry will be represented in the PMC.
Role of Project Management Committee (PMC)steering committee
The Role of the Steering Committee has been weak in the past, but
a more powerful role is being envisaged for the new PMCit in this next
phase that is replacing the Steering Committee. The new PMC will consist
of a reduced number of participants, namely, UNDP (Chair), EAD, IUCN, Ministry
of Environment, Local Government and Rural Development and PTCL. Other
members, such as the Secretary, Ministry of Information, may be invited
depending on the agenda of the meeting. The PMC will have the authority
to take decisions concerning overall project implementation and direction.
For this purpose, IUCN is to provide reports containing comprehensive
and up to date financial information. The PMC steering committee will meet
once/three times the first a year and twice the second year.
Role of Programme Director
The Programme Director is responsible for the day to day management
of the project and in ensuring that project activities are following the
work plan. S/he is responsible for keeping all parties informed of SDNP’s
activities through regular formal and informal reports. A complete job
description is available in Aannex II.
Role of target beneficiaries clients
The target group/clients are is expected to be an active members of
the project. They may be invited to join meetings of the represented on
the PMC Steering committee. At each node, a quarterly meeting of the target
group will be held to discuss common implementation problems especially
regarding the information services component. The meeting will be organized
by the Coordinators. Minutes will be circulated to all relevant parties.
As part of the information strategy, a few target organizations will be
selected to act as "partners" and SDNP will work closely with them to develop
and implement an information strategy, which they will then help in extending
to other organizations. Role of management committee
A management committee consisting of representatives of Ministry
of Environment, UNDP, IUCN and SDNP will meet once every six months to
discuss issues related to the project. Meetings will be convened by the
Programme Director.
8. Counterpart support capacity
IUCN has provided satisfactory support during the previous phase. It
is recommended that IUCN continue as sole sub-contractor during Implementing
Agency for this phase. IUCN is in a strong position to facilitate the work
of SDNP and assist in the various sectors that SDNP will operate inand
with the institutions. Annex VI ("Request for Waiver") provides the detailed
justification for waiving the normal requirement for competitive bidding
for sub-contracts above US$ 100,000 for UNOPS executed projects.
C. DEVELOPMENT OBJECTIVE
The development objective of the project remains the same which is
to promote sustainable human development and the implementation of Agenda
21 through the NCS in Pakistan by facilitating increased access to information,
knowledge and expert advice and by increased communications between stakeholders
locally, nationally and globally. Another objective is to strengthen the
capacity of organizations in Pakistan to package, access and disseminate
deal with information. These efforts will be concentrated on, but not limited
to, organizations working in the field of sustainable human development.
D. IMMEDIATE OBJECTIVES, OUTPUTS AND ACTIVITIES
This section describes the immediate objectives, activities and outputs
of this phase of the project.
Objective 1: Improved access to existing information by
setting up SDNP as a source of reliable information about Ssustainable
Human Ddevelopment in Pakistan
Output 1.1 An SDNP web server with information on sustainable human
development established.
Activities: Carry out an assessment of the market of the necessary equipment.
-
Procure necessary equipment.
-
Setup the SDNP web server in Islamabad.
-
Contact relevant organizations to establish pointers to relevant sustainable
human development information in Pakistan.
Output 1.2: Target beneficiaries will have access to local and international
mailing lists and newsgroups.
Activities: Set-up mailing lists on relevant topics (some of these are
already setup e.g. Environment, Sustainable Ddevelopment, Health, Economics,
Women Iissues, and Information ttechnology, etc.).
-
Select the relevant Internet newsgroups, get a newsfeed and distribute
it to interested parties.
-
Select Internet mailing lists and distribute them locally gateway them
to news groups.
-
Establish gateway news groups to mailing lists if there is demand among
the target organizations.
-
Maintain and distribute to target organizations updated lists of the available
news groups/mailing lists with information about their topics of discussion.
-
Maintain archives of local mailing lists on the web server, where they
can be searched.
-
Provide assistance to new users to access these information resources.
Output 1.3: Disseminate information on Sustainable Human Development.
Activities: Continue to facilitate the existing Pakistan-wide off-line
news groups conferences on more than 30 different topics ranging from computers
to environment.
Encourage newsletters and other publications to publish on SDNP,
such as the SDPI weekly newsletters and other digests already available.
Output 1.4: Develop capacity to assist institutions in a national emergency
or accident.
Activities: Use the electronic networks to assist institutions by providing
the latest technical information on an emergency.
Output 1.5: Awareness of and demand for Ssustainable Human Ddevelopment
information services created.
Activities: The project will encourage the use of electronic communication
and networking for development purposes.
Conduct (at least two) seminars at each SDNP node on Internet
and e-mail; only one in Quetta.
Conduct (at least two) seminars at each SDNP node on publishing
information on the Internet (creating web pages, converting existing data
into web-publishable formats, maintenance of web pages, etc.); only one
in Quetta.
Make sure that the schedules for these seminars are published
well in advance.
Output 1.6: IUCN’s environmental libraries to provide information
on sustainable human development.
Activities: IUCN Pakistan’s libraries will provide some of the
information needed for SDNP to act as a meta-repository. Some of this information
may be available on-line (such websites would be indicated to SDNP), whereas
in other cases, the information would have to be put on-line – however
in either case IUCN would be able to provide the information.
For this purpose, information assistants/librarians,specialists
will be hired in a phased manner for Karachi, Islamabad, Peshawar and Quetta.
Karachi 24 months
Islamabad 2324 months
Peshawar 1624 months
Quetta 712 months
Objective 2: To build capacity among target beneficiaries
in accessing electronic networks for information.
Output 2.1: Approximately 270 persons (10 participants per workshop
x 27 workshops) are trained in how to access information from the Internet.
Activities: Prepare Terms of Reference (TORs) for the group training
workshops in the use of the Internet and electronic networks for accessing
information.
Contact the commercial Internet service providers for assessing
the possibility of sub-contracting these services to them.
If feasible, sub-contract some of these services to the commercial
service providers. Otherwise, the SDNP staff, staff from the provincial
information centers or the master trainers will carry out this training.
If feasible, conduct training on-site at the target organizations.
Output 2.2: Approximately 30 master trainers trained in certain
target organizations to train people in the use of the Internet.
Activities: Work with staff at the provincial information centers and
other organizations so they are capable of conducting this training.
At the training programmes, emphasize that the people attending them
should be capable of going back and training others in their own organizations
and elsewhere.
Objective 3: To build capacity among target beneficiaries
to organize and disseminate information
Output 3.1: Five information centers in the provinces functional. These
centers will be operational as follows:
Islamabad May 1998-June 1997
Karachi July 1998August 1997
Lahore September 1998-October 1997
Peshawar December 1998- January 1998
Quetta September 1999April 1998
Activities: Initiate discussions/negotiations with potential organizations
to become provincial information centers.
Obtain agreement and sign sub-contracts with selected organizations
and assist them in becoming provincial information centers.
Assist these five organizations in reaching out to other institutions:
in conducting training in accessing the Internet and electronic publishing.
Output 3.2: The 70 target Seventy organizations assisted in providing
their information electronicallyImproved access to existing information;
in particular, information located on the Internet, for at least 70 target
organizations. [this output is not achieved through the activities given
below – it should be rewritten as "a number of organizations assisted in
providing their information electronically"]
Activities: Assist organizations to publish information on the
web, either using SDNP or any commercial ISP.
Assist target organizations in putting information already in
electronic form on-line, thus making it available to a larger number of
people. This may involve showing them how to use the appropriate conversion
utilities.
Assist target organizations and others holding information in non-electronic
form, to develop a strategy for making this information available on-line.
Objective 4: To promote connectivity among the target group
so that they can effectively use electronic information available on SDNP
and the Internet.
Output 4.1: Creation of a provincial SDNP node in Quetta.
Activities: Select a site, hire staff and procure equipment (for off-line
connectivity).
Start providing an e-mail service to users.
Provide information service (mailing lists, newsgroups, local web
server) to users.
Output 4.2: Provide connectivity and training to the 70 target organizations
working in sustainable human development
Activities: Select the above institutions.
If necessary, provide them with relevant equipment such as modems
and upgrading of PCs.
Provide them with connectivity.
Provide them with the initial training and assistance in using
this facility.
Output 4.3: Ensure optimum utilization of resources, such as the 64kbps
link, providesion e-mail and Internet connectivity to SDNP users.
Activities: Operationalize the 64 kbps bandwidth by signing agreement
with UNDP/UN Agencies and a commercial ISP.
-
Install new telephone lines from the new SDNP office tat o the UN House
(Saudi-Pak Tower).
-
Sign agreement with an ISP for the domestic connectivity.
-
Procure the new computers/communications equipment
-
Provide facilities to target users for hosting web sites.
-
Market and promote the new services of SDNP.
-
Undertake the necessary office renovations.
-
Obtain the required licenses.
-
Provide Internet service, including web access, to users.
The following targets, in terms of SDNP clients, have been set:
Location Novug 1998 DEC 1997 Octoberul 1999 DEC 1998Marchec 1999 APRIL
1999 2000
------------------------------------------------------------------------------------------------
Islamabad
e-mail 2600 3800 4100
Internet 200 500 500
Karachi 2600 3800 4100
Lahore 833 1033 1083
Peshawar 163 238 256
Quetta 50 100
-----------------------------------------------------------------------------------------------
Total 6396 9421 10139
Marketing and promotion will have to be undertaken to promote
the services of SDNP.
Provide facilities for hosting web sites.
Operationalize the 64 kbps bandwidth c.
Sign agreement with an ISP for 19.2 kbps for the domestic connectivity.
Install the new telephone lines.
Procure the new computer/communication equipment
Undertake the necessary office renovations.
Obtain the required licenses.
Provide Internet service, including web access, to users.
Output 4.4: Provide assistance to the government in policy-making in
the field of telecommunications, information and networking.
Activities: Have discussions on SDNP mailing-lists on new or proposed
legislation in the relevant areas.
Study and actively engage in dialogue on the existing political
situation in Pakistan and other countries on thewith regard to legislation
and policies concerning the electronic networking environment.
Submit recommendations (backed by the PMCSteering Committee and/or
other "experts" in the field) to the relevant government bodies.
Output 4.5: Creation of a neutral "Internet Exchange" in Pakistan for
the different ISPs to be able to exchange traffic for each other within
the country, without having to go via the expensive international links.
Activities: Promote discussions on mailing lists (and maybe mass
media) about the need for and benefits of such an exchange.
Initiate discussions with the relevant bodies (ISPs, PTC etc.)
about this proposal. If feasible, facilitate signing of agreement for a
designated organization to host the exchange.
Objective 5: To have a plan for a sustainable SDNP by
the end of this project.
Output 5.1: SDNP services sustainable after the life of this project,
by having SDNP consider the viability of various optionsbecome an independent
organization fully capable of sustaining its operations.
Activities: A detailed feasibility will be undertaken during this transition
period (up to Oct. 1998June 1999) to come up with the best option for sustaining
the current work of SDNP after the 2-year period. The study will focus
on how SDNP can become a self sustaining not-for-profit entity promoting
its current development objectives after the 2-year period. It will also
consider the possibility of SDNP as an organization shutting down or moving
on to different activities and letting the different SDNP members (who
have been trained and started off by SDNP) continue with this task of keeping
information updated.
An Independent end-of-project mid-term review of project activities
evaluation will be carried out.out by the IUCN/SDNP team with the management
committee to redirect activities if felt necessary.
Output 5.2: Capacity developed, at SDNP and other organizations, to
continue with these activities even after the duration of this project.
Activities: SDNP staff and those at the provincial information centers
will be trained, so as to be capable of providing training/assistance in
the field of information networking.
SDNP will develop an efficient system, which can continue after
the life of this project if felt necessary. It is hoped that SDNP will
find other "champions" to continue its activities even after UNDP funding
runs out.
SDNP may decide to expand the scope of the project and include
more beneficiaries and extend the service to other areas of development.
Output 5.3: Revenue-generating activities of SDNP identified and marketed.
Activities: Some SDNP activities (e.g. helping an organization develop
an information plan) are more "marketable" than others. These activities
should be noted and explored during the course of the project.
UNDP can use SDNP to handle the information needs of its other
projects, e.g. the Regional Governance Fsacilitygovernance project.
Most recent UNDP projects have some sort of an "information" component,
much like they have a "communications" component. SDNP can assist some
of these projects inwith developing this component.
INPUTS
Inputs to the project are explained below.
1. UNDP and SDNP inputs
UNDP will provide funding for certain activities and e-mail and interest
income will fund other activities the Information Services component of
the extension phase as indicated in the budget.UNDP/Pakistan will fund
certain activities with TRAC resources while others will be funded by project
generated e-mail income and interest during the previous phases and estimated
revenues to be generated in the two year extension period. The details
of the budgetary calculations, and working assumption, have been prepared
by a consultant, based on a market survey and consultations with SDNP,
IUCN and UNDP staff. Operational data has been provided by the SDNP office
in Islamabad while financial data has been provided by IUCN Finance Department
in Karachi. A detailed report of development costs and cash-flow analysis
has been prepared in a separate document available with UNDP Pakistan and
IUCN Pakistan. It will also be part of the management committee to oversee
the project. It will help in discussions and negotiations with the government
regulatory authorities, as and when needed.
The total project expenditures for the two years extension are US$ 1,090,499.
These expenditures will be covered as follows:
PAK/95/006 (carry-over) US $ 40,000
PAK/95/006 (increase) US $ 200,000
Project generated e-mail revenues and interest from the previous
phases
(total income as at 31 December 1997
converted at US $ 1 = Rs. 43.90): US $ 500,000
Estimated project revenues generated during the next two years
through its
various activities and services US $ 350,449
The inputs covered by UNDP and SDNP financial inputs will fall under in
the following components:
Personnel/sub-contracts
The Project Director based in Islamabad will be responsible for the
overall management of the project. In addition, he/she will study the information
networking and telecommunication policy in Pakistan, and compare it with
the situation in other countries. He/she will develop recommendations which
could be debated by the SDNP members on mailing lists and provide input
to the government as well as raise public awareness.
IUCN will provide management and administrative support to the project,
comprising the part-time use of the Head and of a Coordinator of the Communications
Unit, a driver, guard and cleaner. IUCN will also be responsible for maintaining
the project accounts. The Project Accountant will maintain the accounts,
especially the revenue generated and allow the Project Director to tailor
activities based on the current financial status. An administrative assistant
position to support the project and deal with users accounts has also been
established.
The Information and Connectivity Coordinators in Islamabad will be the
senior most people within their group and responsible for coordinating
the activities of the others.
Each SDNP node (i.e. the SDNP centers in Karachi, Peshawar, Lahore
and Quetta) will also have a Coordinator and one or more User Support Staff
who will assist users with their information requests and training, and
also provide technical support in the case of connectivity problems. Additional
User Support Staff will be recruited as and when the number of users and
the workload is large enough to justify them.
Information Assistants/Librarians. A person in each city, will assist the
information coordinator in searching for non-electronic material that needs
to be put on-line or within web pages.
The current strength of the project staff is 9. Up to an additional
17 persons may be recruited, mainly for providing information services.
Detailed job descriptions are provided in Annex II.
An information services team -- consisting of one Information Specialist
and one Networking Trainer -- in each city of operations is also required;
however, in all other cities than Islamabad, these will not be recruited
as project personnel, but sub-contracted to the partner/target organizations.
Also this team will not be located at the SDNP office, but at a suitable
"partner organization" who will host the provincial information center.
Their phasing is as follows:
Islamabad 23 months
Karachi 21 months
Lahore 19 months
Peshawar 16 months
Quetta 7 months
The staffing details are as follows:
POSITION ISLAMABAD KARACHI LAHORE PESHAWAR QUETTA
Programme 1 (21)
Director
Accountant 1 (23)
Admin.
Assistant 1 (23)
Coordinators 2 (24) 1 (23) 1 (23) 1 (23) 1 (7)
User Support 4 (24) 3 (24) 2 (24) 1 (24) 1 (7)
Information 1(23) 1 (24) 1 (16) 1(7)
Assistant/librarian
Information 1 (23)
Specialist
Networking 1 (23)
Trainer
Total staff = 123 5 3 3 3 = 26
Office accommodation
SDNP will require new premises in Islamabad. IUCN is expected to provide
an additional space or new premises at Karachi and Peshawar. In Lahore,
Edunet or a suitable location will be identified for the office.
Networking equipment
This will mainly include computers for hosting the web sites, and other
networking equipment such as modems and routers. In some of the cases,
the offices need some renovation and/or expansion; this has been provided
for. The main equipment for Internet connectivity in Islamabad will be
placed in the UN House.
Seminars and workshops
Assistance of local institutions may be required for holding seminars
etc..
Communication
Communication costs for the Internet connection, and for intercity VSAT
links have to be paid for.
License fee
It may cost approximately Rs. 505,000 and has to be obtained. There
is a possibility of SDNP obtaining a license free of charge, but that is
not certain yet.
IUCN input
In addition to providing management and administrative services, IUCN's
input will also be required in providing guidance on information relating
to Ssustainable Human Ddevelopment. In addition UCN’s its many contacts
established over the years will be a great asset to the project when approaching
the government or non-governmental organizations. Its experience in the
area of environment and NCS will also be of great help. IUCN will also
participate in the management committee.
Target beneficiaries input
The target beneficiaries are expected to provide the necessary staff,
office space, furniture, utilities, stationery and other back-up for the
support and technical assistance provided by SDNP.
4. Government input -- Ministry of Environment, Local Government
and Rural Development
The Ministry is the Government Cooperating Implementing Agency of the
project and its input will be needed during the implementation stage. Help
will be needed from the Ministry when dealing with government institutions.
Financial
The total project expenditures for the two years extension are US$ 1,257115,422.
These expenditures will be covered as follows:
PAK/93/003 US $ 40,000
PAK/95/006 US $ 450,000 ?
E-mail revenues and interest incurred during the previous phases
(total income as at 31 December 1997
converted at US $ 1 = Rs. 45/=39.9): US $ 500,000
revenues generated during the next two years through its
various activities and services US $ 307,000
the first months of , and will furnish a list of assets annually
and assets and liabilities.
Personnel
The Programme Director based in Islamabad will be responsible for
the overall management of the project. IUCN will provide management and
administrative support to the project, comprising the part-time use of
the Head and of a Coordinator of the Communications Unit, a driver, guard
and cleaner. IUCN will also be responsible for maintaining the project
accounts. IUCN will be assisted by the Project Accountant in this regards,
who will maintain the accounts, especially the revenue generated and allow
the Programme Director to tailor activities based on the current financial
status. An administrative assistant position to support the project and
deal with users accounts has also been established.
Secretary
In addition, a Policy Assistant post has been established. This policy
assistantS/he will study the information networking and telecommunication
policy in Pakistan, and compare it with the situation in other countries.
S/he will work with the Programme Director to create recommendations which
could be debated by the SDNP members on mailing lists and provide input
to the government as well as raise public awareness. The reason a full-time
post has been included is that this is one of the areas in which SDNP has
a unique position because of its practical experience with networking,
as well as an impartial position. The work of this advisor can also lead
to further work in academic institutions by others. Total of 23 months
input has been provided.
The Information and Connectivity Coordinators in Islamabad will be the
senior most people within their group and responsible for coordinating
the activities of the others.
Each SDNP node (i.e. the SDNP centers in Karachi, Peshawar, Lahore
and Quetta) will also have a Coordinator and one or more User Support Staff
who will assist users with their information requests and training, and
also provide technical support in the case of connectivity problems. Additional
User Support Staff will be recruited as and when the number of users and
the workload is large enough to justify them.
The current strength of the project staff is 9. Up to an additional 14
persons may be recruited, mainly for providing information services. Detailed
job descriptions are provided in the annexes.
An information services team -- consisting of one Information Specialist
and one Networking Trainer -- in each city of operations is also required;
however, these will not be recruited as project personnel, but subcontracted
to the partner/target organizations. or commercial service providers,
if this is feasible. ? Also this team will not be located
at the SDNP office, but at a suitable "partner organization" who will host
the provincial information center. Their phasing is as follows:
Islamabad 23 months
Karachi 21 months
Lahore 19 months
Peshawar 16 months
Quetta 13 months
The staffing details are as follows:
POSITION ISLAMABAD KARACHI LAHORE PESHAWAR QUETTA
Programme 1 (214)?
Director
Policy
Assistant 1 (23)
Accountant 1 (23)
Admin.
Assistant 1 (23)
Coordinator 1 (224) 1 (23) 1 (23) 1 (23) 1 (13)
User Support 4 (24) 3 (24) 2 (24) 1 (24) 1 (13)
[[Information 1(24) 1(24) 1 (24) 1(12)
Assistant/librarian]]
Information 1 (23)
Specialist
Networking 1 (23)
Trainer
Total staff = 113 5 3 3 3 = 272
For the purpose of budgeting and accounting, since most staff
will be involved in both the connectivity and information components, personnel
costs have been split roughly between information and connectivity, in
proportion to the estimated fraction of their work in each area. The details
of this apportionment are provided in Annex V.
Office accommodation
IUCN premises will be used at Islamabad , Karachi, and Peshawar. IUCN
is expected to provide an additional space or new premises at Karachi and
Peshawar. Additional office space will be made upstairs in the Islamabad
office by closing the lounge. In Lahore, Edunet or a suitable location
will be identified for the office.
Networking equipment
This will mainly include computers for hosting the web sites, and other
networking equipment such as modems and routers. In some of the cases,
the offices need some renovation and/or expansion; this has been provided
for.
Seminars and workshops
Assistance of local institutions may be required for holding seminars
etc..
Communication
Communication costs for the Internet connection, and for intercity VSAT
links have to be paid for.
License fee
It may cost approximately Rs. 505000 and has to be obtained. There is
a possibility of SDNP obtaining a license free of charge, but that is not
certain yet.
F. RISKS
The current SDNP is a very innovative project in the sense that a
large part of the project financing is linked to the revenues generated
by the project. This poses a financial risk in addition to the many operational
risks. These risks are listed below:
Financial
As designed the project needs to generate a large percentage of its
financing as revenues if it is to successfully implement the planned activities.
Revenues have been estimated conservatively; yet there is always a risk
of the project being unable to raise the required revenues.
Technology
Technology moves rapidly in this area. This may make the SDNP equipment
or plans obsolete. This project does not cater for the purchase of new
equipment to keep up with changes in the technology.
Policy
A change in Government policy may have an adverse impact on the project.
This can be tackled to some extent by proactively engaging the relevant
government departments in discussions; e.g. granting a license for network
services to SDNP, but there is a risk.
-
Competition
Keen competition is expected from the other service ISPs. This competition
may result in the lowering of prices and improvement in performance. SDNP
revenues will be adversely aeffected due to the lowering of prices in the
market.
Outputs
The project has a large number of outputs. Most of the outputs are reasonable
and can be readily achieved. Some are more ambitious (e.g. policy input
to government, assisting formation of a Pakistan Internet Exchange etc.)
and the project may not succeed in actually achieving these, but it is
still a progress if it encourages public debate which leads to action in
a longer time-frame. The number of users estimated may be too high; leading
to reduction in expected revenues (which, in turn, will affect other activities).
A phased/modular approach to Modular approach?the projected outputs/activities
will be taken by the project [[ if the number of cities are scaled down]]
as a means of keeping a reality check on the state of both the connectivity
and the information content market. This will help in assessing project
sustainability at the end of the first year, and will feed into the feasibility
and the business plan that would be prepared at this period.
Sustainability of SDNP after 2 years
Some SDNP activities are sustainable and can continue even after UNDP
funding runs out. The question of what to do after two years is valid,
but cannot be answered now; a feasibility study at the end of one year
and progress review meetings should help decide the course of future actions.
Institutions not interested in Information services
There is a risk that the institutions do not show much interest
in sharing information and in developing new databases. There is little
risk in the training component as most institutions are keen on getting
training.
-
Staff continuity
In the present status there is great dependency on one or two
individuals. Availability of project staff with the requisite skills is
necessary for project success.
Delay in inputs
The project has a very short time to achieve its objectives and
outputs. If staff recruitment and input of other items is not on time then
it may lead to lower outputs.
Non-availability of telephone lines
The projects output depends to a great extent on the availability
of telephone lines. If these are not provided then the activities can suffer
a major setback.
G. PRIOR OBLIGATIONS AND PREREQUISITES
IUCN will open a separate account with an opening balance equivalent
to all the income plus interest earned by SDNP as of 31 December 1997.
IUCN together with UNDP will prepare a financial reporting and monitoring
system for the project. It must provide the necessary information on income
and expenditures., A list of assets will also be furnished assets and liabilities
on an annual basis.
Donors to the previous project phase must have no objection to
this extension, as e-mail revenues generated from the previous phase is
being used to cover expenditures during the two year extension. In doing
so, UNDP Pakistan will forward a copy of the project revision document
to the donors/investors, i.e. SDNP in New York and IDRC in Canada, to ensure
that they do not object to this extension.
H. PROJECT REVIEW, REPORTING AND EVALUATION
The current mechanism of review, reporting and evaluation was not
very effective. A better and more effective system is recommended.
The new PMC will play an important role in monitoring the project, as it
will have more authority than the previous Steering Committee.
The project is to be jointly reviewed midway in order to prepare for
a feasibililty studyafter one year by UNDP, MoE.LG&RD, IUCN and SDNP.
. Comments from the target beneficiaries at the time of review can be sought
through e-mail. [[The terminology here should match what has been stated
earlier under output 5.1 on page 18 to prevent confusion on who does the
internal review]]
Feasibility, External Review, Joint review? How many reviews/evaluations?
The second meeting will be held at an appropriate date. The Programme Director
shall prepare and submit to each review meeting a Project Performance Evaluation
Report (PPER). Additional PPERs may be requested, if necessary, during
the project.
The steering committee set up as part of UNDP's requirement for SDNP,
chaired by the UNDP Resident Representative met only twice since the start
of the project. Thus to make it effective, IUCN or the Programme Director
should be made responsible for holding the meeting to which UNDP should
be invited. The views of the target beneficiaries and their input can be
taken through E-mail for the meeting. Meeting should be held once a year.
The informal reporting system was quite extensive but the regular reporting
system was weak, especially the financial reporting. Thus a brief formal
quarterly report needs to be prepared and submitted to the relevant persons
and institutions. A written feedback is essential on the report. The Programme
Director must ensure that a such a feedback is provided even if there are
no comments. The report must include the following:
- Monthly income/expenditure statements sorted, at least, by city (node)
and service component (Information and Connectivity)
- Monthly user statistics
- Annual Fixed Assets position
- Annual Financial Status (Budget/Funds) Reports
A project terminal report will be prepared for consideration at the
terminal review meeting. It shall be prepared sufficiently in advance (at
least 4 months before) by the Programme Director to allow for review by
all the parties.
The project will be subject to an independent end-of-project evaluation
during the last year of the project. The terms of reference, and exact
timing will be decided after consultation between the parties. [[ Please
specify if this will be an external evaluation, who it will be conducted
by and its source of funding . There is no provision for this in the current
budget]]
I. LEGAL CONTEXT
JI. BUDGETS
The UNDP TRAC budget is as follows:
The budget is based on the discussions held with SDNP, IUCN and UNDP
staff. The operational data has been provided by the SDNP office at Islamabad
while the financial data has been provided by IUCN finance department in
Karachi.
UNDP/Pakistan will fund certain activities while others will be funded
by email income and interest from the previous and revised phase. The details
of the budgetary calculations and working assumption upon which they are
based are provided in the annexes.
JK. ANNEXES
ANNEX I: Work Plan
The elements of aA rough work plan has been incorporated in section
D, as a number ofunder the activities. [[Where is this?]] A more
detailed and time bound plan will be is being developed by the project
team, as the first main task. Immediate activities to be undertaken are
as follows:
The recruitment of staff, in particular the Project Director, should
be undertaken immediately, as it has an impact on all the activities. The
recruitment of some of the new staff of the Connectivity Division Activities
can be postponed if a delay is foreseen in getting the infrastructure ready
for the 64kbps bandwidth.
Equipment can be purchased immediately.
The business plan needs to be developed by June 1999October 1998. This
is to provide some time for the Internet services to be operational.
Planing for the Independent end-of-project Evaluation can be initiated
by UNDP 6 months before the end of the project in order to give sufficient
time for coordinating the excercise.
An external evaluation can be undertaken by UNDP 6 months before the
end of the project in order to give sufficient time for taking further
action. After one year ? Ses above
ANNEX II: Job descriptions
[[ Does not match with earlier reference to external evaluation
at end of project]]
ANNEX II: Job descriptions
1. Programmeject Director:
The Project Director will be responsible for the management of the SDNP
project. He/she will report to the relevant unit in IUCN managing the SDNP
on a day-to-day basis, under the overall guidance of the IUCN Country Representative
and the Project Management Committee . Under the overall direction of the
UNDP Resident Representative and the day to day supervision of IUCN, the
Programme Director will be responsible for the management of the SDNP project.
The Projectgramme Director will be expected to have a very good understanding
of the issues related to and if possible the main players involved in promoting
sustainable human developmentsustainable development, a regional
person will not know the players a demonstrated understanding of
the use of information technology for computer mediated communications,
demonstrated and strong managerial skills, have good writing skills, and
have good interpersonal and communication skills along with initiative
and drive.
The Programmeject Director will be responsible for helping to develop,
adapt and implement the programme of work. He or she will be responsible
for managing the SDNP secretariat, for making recommendations regarding
priorities and the expenditure of funds, and for doing this in consultation
with members of an the SDNP Management Committee. Who?
The Programmeject Director will also be responsible for setting up and
managing the information teams in the various centers, and directing their
activities.
The Programmeject Director will also be responsible for developing a
marketing and business plan and/or other plans for the ongoing operation
of the SDNP. He or she will direct the activities of the Accountant and
present the required reports to IUCN and the Project Management Committee
when required. The Programmeject Director will be responsible for submitting
timely reports to UNDP and others as required.
2. Coordinators:
The Connectivity Coordinator: S/he will be responsible for the connectivity
activitiesdivision of the project and will work under the guidance ofreport
to the Programmeject Director. The primary function of the coordinator
will be to ensure the trouble free operation of the network. This would
involve liaison with the vendors providing the 64 K line and the domestic
19.2 Kconnectivity line. S/he will be responsible for developing the necessary
systems and procedures for the safe and reliable functioning of the network.
The coordinator will also recommend actions for the improvement of the
network. S/he will assist the User support staff in trouble shooting. The
coordinator will also manage and supervise the activities of the User Support
staff. In addition he will also keep track of the user statistics of the
network. The Islamabad Coordinator will be the over all coordinator most
senior coordinator ? not necessarily most senior? and will
have the additional duty of coordinating the overall connectivity activitiesdivision.
S/he will formulate the policies and develop the necessary long term and
short term plans for the connectivity activitiescomponent. The coordinator
will also assist the information team in searching for information on sustainable
human developmentsustainable development on the Internet and advise on
the most efficient way for disseminating the information. The Coordinator
will need to have a strong linkage with the information services.
The Information Coordinator: This person will be responsible for developing
and managing the information component of the SDNPfor the over all coordinationng
of all the information work of SDNP. This will involve surveys of users
and producers of information within the organization, and plans for electronic
dissemination of the information. He/she will manage and work closely with
the Information Team in Islamabad. The Information Coordinator and Information
Team will train staff of sub-contracted organizations (provincial information
centres) in publishing information, searching for it and assisting these
institutions implementing the information component in each of the cities.
While working closely the Information Team and the provincial information
centers (sub-contractors), the Information Coordinator will also have the
responsibility to supervise the performance. S/he will be responsible for
analysing the SHD information needs of the target beneficiaries and of
ensuring that pertinent material is put on the SDNP web server at least.
The Information Coordinator will report to the Project Director
3. Information Assistants/ (librarians): A person in each city, will
assist the information coordinator in searching for non-electronic material
that needs to be put on-line or within web pages.
43. User support staff:
Under the supervision of the local Coordinator and/or his or her designated
representative, the User Support staff will be responsible for assisting
SDNP users. A small part of the assistance will be with connectivity-related
problems, but the major part of the work will be to help users with their
information queries; teach them how to look for information on the Internet
in Pakistan and outside, some basic training in creating web pages, maintaining
resource lists (lists of mailing lists, newsgroups etc.) They will also
assist the Information Services Team as and when required, with training
or other activities.
Based on the level of activity, the number of such staff will be decided
by the Coordinator at each node in consultation with the Projectgramme
Director.
54. Information services team/sub-contracts:
This will consist of two peoplestaff members in the SDNP Office in
Islamabad (an Information Specialist and Networking Trainer) and sub-contracts
(to provincial information centres) in each of the other target cities.
The team/sub-contractors will be responsible for developing and managingimplementing
the information component ofin each of the target citiesthis project. They
will work closely with the provincial information centers to assist that
institution develop and implement an information policy. This will involve
surveys of users and producers of information within the organization,
and plans for electronic dissemination of the information. They will train
staff at the organization in publishing information as well as in searching
for it.
Once thise provincial information centers is have been established,
the Information tTeam will proceed to use this expertise gained to extend
the model to other organizations in the region. They will also conduct
training programmes to further spread this knowledge.
The team will have a good understanding of and demonstrated experience
using computer mediated communications, especially computer networking.
The ideal candidates will also have a good understanding of sustainable
human developmentsustainable development and of the information needs of
the user community.
They will have good communication skills and the ability to express
himself or herself in writing and orally. Good presentation skills are
necessary, as it will be necessary for this team to train other users.
Flexibility and willingness to undertake other tasks as necessary will
also be required.
65. Accountant
The SDNP Accountant will keep track of all the project revenues and
expenses. He will provide reports to the Programmeject Director in whatever
format required, and assist in financial planning for the project.
76. Administrative Assistant
S/he will assist the SDNP team in the Administrative running of SDNP.
S/he will be in charge of all secretarial duties; in addition to the
following: assisting with creating user accounts and collection of fees
from users, documentation management and filing; storekeeping of office
and working materials, supplies and consumable. User support should do
this.
s/he will provide some backstopping to the user support staff if required.
S/he will sometimes be delegated for duties related to demonstration
or presentations of the SDNP services and monitoring of the needs of users.
No
S/he should have computer skills on word processing, spreadsheet, databases
and computer graphics. Knowledge of accounting and office practice will
be an added advantage. Why databases
Usual communication skills and the ability to express self in writing
and orally are useful. Good presentation skills are also needed.
Why?
7. Policy Assistant:
Under the guidance of the Programme Director, the policy researcher
will study the information networking and telecommunications policy in
Pakistan. S/S/he will use the Internet to get information about the situation
in other countries, and also contact people in Pakistan working in relevant
areas. The output of this activity would be to generate papers or proposals
that could be debated by SDNP members and finally presented to government.
This work could also lead to further studies in academia or policy institutes.
8. Quetta team: is Quetta different from the others? Quetta will not have
any information activity
The SDNP team at Quetta will consist of two people: a coordinator
and a user support officer. The coordinator will be responsible for directing
activities of the team. Together, they will be responsible for creating
and running the node. This will involve setting up systems to provide (at
least) email connectivity, marketing it to local users and providing new
information services when possible. The coordinator will also be responsible
for reporting to the Projectgramme Director periodically. In addition,
there would be an information assistant.
ANNEX III. Schedule of project reviews, reporting and evaluation
Details provided in section H.
ANNEX IIIIV. Financial and accounting arrangements
Project Account
A separate project account will be maintained for the project.
The accounts must clearly indicate the balance amounts available on each
budget line.
Installments
UNDP/Pakistan will advancereimburse IUCN funds for the services covered
by the sub-contract under PAK/95/006, Budget Line 213.01. IUCN will provide
quarterly financial statements of expenditures. For details see Annex VII
"sub-contract".
The revenue and interest generated during the previous phase of the
project will be deposited in the SDNP project account at the beginning
of this phase. In addition, all revenues generated from the connectivity
services during the extension phase are to be deposited in the SDNP project
account as well.
Financial Statements and Reporting
IUCN will maintain the accounts as per the standard accounting procedures.
IUCN will submit a complete financial statement with the quarterly progress
report. This financial statement will consist of monthly expenditure and
income statement. IUCN will also submit an annual expenditure and income
statement. In addition, IUCN will also furnish annually a list of fixed
assets relating to the project.
Equipment purchases
Under the project, SDNP will be entitled to duty free import of equipment
for the project. However, it can opt to buy from the local market if conditions
are more favorable.
Reallocations of budget heads
Given the nature of the project and the rapidly changing environment,
the project management has the flexibility of reallocating up to 10% of
a budget line provided the total project amount is not exceeded.
[[IUCN would require approval of the Project
Management Committee for reallocation of budget lines in excess of a variation
of 10%?]]
ANNEX IV. Budget Estimate and AssumptionsBudget
estimates and assumptions
BUDGET FOR THE ACTIVITIES TO BE FUNDED BY UNDP/Pakistan
1. SDNP financing arrangement and funding gap.
2. PAK/95/006 (Sub-contract only)
3. SDNP cash flow summary
4. Detailed Recurring/Development Budget by nodes
5. Revenues Estimation
BUDGET FOR THE ACTIVITIES FUNDED BY PROJECT REVENUES
AND INTEREST.
1. SDNP financing arrangement and funding gap
2. Budget
3. SDNP cash flow summary
4. Detailed Recurring/Development Budget by nodes
5. Revenues Estimation
BUDGET FOR THE TOTAL PROJECT
1. SDNP financing arrangement and funding GAP
2. Budget
3. SDNP cash flow summary
4. Detailed Recurring/Development Budget by nodes
5. Revenues Estimation
UNDP will provide funding for certain activities
while project generated e-mail income and interest will fund other activities
of the extension phase. The tabele below presents the overall budget for
all costs to be incurred during the two year extension of the project.
(it does not include costs already incurred by SDNP during the previous
phases). The total budget for the two year period is US $ 1,090,449. TRAC
will fund US $240,000 while the remaining costs will be covered by the
income and interest generated from e-mail services.
|
Table:
SDNP: Total budget for 1 April 1998 - 31 March
2000 (US $)
|
|
|
BL
|
Description
|
Budget
|
Funding/Comp.
|
|
10
|
Project personnel
|
|
|
|
11
|
International Experts
|
|
|
|
11.01
|
Consultant (Feasibility)
|
12,500
|
Email
|
|
11.02
|
Project Director
|
89,000
|
TRAC (BL21.01)
|
|
13
|
Admin support personnel
|
|
|
|
13.01
|
Admin. Assistant/Support
|
26,400
|
Email
|
|
13.02
|
Accountant
|
9,000
|
Email
|
|
15
|
Travel
|
|
|
|
15.01
|
International (w'shops)
|
-
|
|
|
15.02
|
In country
|
15,975
|
TRAC (BL21.01)
|
|
16
|
Evaluation
|
|
|
|
16.01
|
Evaluation
|
20,000
|
TRAC (BL16.01)
|
|
17
|
NPPP
|
|
|
|
17.01
|
Project Director
|
-
|
|
|
17.02
|
Coordinators (All cities)
|
80,375
|
Email
|
|
17.03
|
User Support Staff
|
65,700
|
Email
|
|
17.04
|
Policy Assistant
|
-
|
|
|
17.05
|
Information Specialist(Isb)
|
18,000
|
Email
|
|
17.06
|
Networking Trainer (Isb)
|
11,500
|
Email
|
|
17.07
|
Information Coordinator-Isb
|
30,000
|
Email
|
|
17.08
|
Head Comm Unit (IUCN)
|
11,040
|
Email
|
|
17.09
|
Coord. Comm Unit (IUCN)
|
9,000
|
Email
|
|
17.10
|
Interns (Canadians)
|
1,875
|
Email
|
|
17.11
|
Library Staff
|
16,500
|
Email
|
|
17.99
|
Sub Total
|
243,990
|
|
|
19.99
|
Component Total
|
416,865
|
|
|
20
|
Sub-Contracts
|
|
|
|
21.01
|
Karachi
|
38,250
|
TRAC (BL21.01)
|
|
21.02
|
Lahore
|
29,750
|
TRAC (BL21.01)
|
|
21.03
|
Peshawar
|
20,500
|
TRAC (BL21.01)
|
|
21.04
|
Quetta
|
8,625
|
TRAC (BL21.01)
|
|
29
|
Component Total
|
97,125
|
|
|
30
|
Training
|
|
|
|
31.01
|
Group Training
|
12,963
|
Email
|
|
31.02
|
Seminars
|
5,000
|
Email
|
|
31.99
|
Sub Total
|
17,963
|
|
|
45.01
|
Local equipment
|
|
|
|
46.02
|
International equipment
|
|
|
|
49.99
|
Component Total
|
196,300
|
Email
|
|
50
|
Miscellaeneous
|
|
|
|
51
|
Operating costs
|
|
|
|
51.01
|
Rental (All cities)
|
52,750
|
Email
|
|
51.02
|
Utilities
|
24,025
|
Email
|
|
51.03
|
Telephone
|
18,875
|
Email
|
|
51.04
|
Misc. Office Costs
|
30,708
|
Email
|
|
51.99
|
Sub Total
|
126,358
|
|
|
52
|
Publications
|
|
|
|
52.01
|
Publications
|
1,663
|
Email
|
|
53
|
Networking costs
|
|
|
|
53.01
|
New York Dialing
|
-
|
|
|
53.02
|
In Country Direct Dialing
|
8,250
|
Email
|
|
53.03
|
19.2 K (Domestic Conn.)
|
47,600
|
Email
|
|
53.04
|
64 K (Internet Conn.)
|
61,100
|
Email
|
|
53.05
|
Tel rental network
|
600
|
Email
|
|
53.06
|
License Fee
|
12,625
|
Email
|
|
53.07
|
UNDP CO Sundries
|
4,000
|
TRAC (BL53.01)
|
|
53.99
|
Sub total
|
134,175
|
|
|
54
|
IUCN Management Fee
|
100,000
|
TRAC (21.01)/Email
|
|
59
|
Component Total
|
234,175
|
|
|
99
|
Total Costs
|
1,090,449
|
|
|
|
|
|
|
SDNP: Funding/Income 1 April 1998 -31 March
2000
|
|
|
Total costs funded by TRAC
|
240,000
|
|
|
PAK/95/006 carry-over
|
40,000
|
|
|
PAK/95/006 additional
|
200,000
|
|
|
Total Costs funded by e-mail income
|
850,449
|
|
|
Income generated as at 31 Dec 1997
|
500,000
|
|
|
Estimated income - extension phase
|
350,449
|
|
|
Total
|
|
1,090,449
|
|
ANNEX VI Sub-contract (draft)
| Project Summary Status |
Africa |
Arab States |
Asia |
Europe/CIS |
LA/Caribbean |
|